Dubai Harbour Project
2 no’s LSI barges were hired to help finish of the last stage of the Dubai Harbour project where LSI has now worked for 4 different clients on 5 occasions. The barges worked for a large and well respected Marine civil contracting company based in the UAE which has been a client of LSI for more then 20 years.
Barge Hamriyah Ann was hired out as a flattop barge for transporting concrete Quay wall blocks. Before going to the project the barge had been drydocked and passed it’s Bureau Veritas 5 year Special Survey.
Barge Creek Ann 2 was hired out as a spud barge with sidewall, concrete deck and self lifting spuds. Onsite a PC 850 excavator was installed and the vessel/excavator commenced dredging works. Before going to site our Technical department had done significant modification works in order to get the barge ready for the project.
Here with also some pictures of the vessels when they were being prepared prior going on-hire.